5/10 Marla House Construction Cost in Pakistan
Written by: Neelam Shahzadi
Reviewed by: Majid Hussain
Are you planning to build your dream house in Pakistan? If yes, you must know the 5 Marla house construction cost in Pakistan. Building a house is a major milestone and expense for most people, and knowing what the project costs beforehand is essential.
The construction prices for 5 Marla houses vary depending on various factors such as location, materials, labour, and designs. Let us dive into the 5 Marla house construction costs and see the 10 Marla house construction cost in Pakistan.
5 Marla House Construction cost in Pakistan
5 Marla is a popular plot size for house construction in Pakistan. The construction cost of a five-marla house in Pakistan varies by location. However, on average, the estimated cost is around PKR 25-30 lakh. This includes construction materials, labour, and other miscellaneous expenses.
Regarding the design of a house in Pakistan, you can choose from various designs that suit your preference. The five Marla house design options include single-story and double-story houses.
In terms of construction materials, the cost depends on the type and quality of materials used. The grey structure of the house, which includes the foundation, walls, and roof, is the most expensive part of the construction process. The cost of the grey structure for a 5-Marla house in Pakistan is around PKR 15-20 lakh.
Construction Cost for 5 Marla House
If you want to build a double-storey house on a 5-Marla plot, the estimated cost is around PKR 35-40 lakh. The double-storey five-Marla house design includes a detailed plan for the first and second floors and the staircase design.
Here is a detailed breakdown of the construction cost for the 5 Marla house:
Materials | Rate (Pkr) | Quantity | Cost (Pkr) |
---|---|---|---|
Foundation & Structure | |||
Bricks + Rorhi | 26/Unit | 56262 | 1462812 |
Cement | 1150/Bag | 605 | 695750 |
Sand | 87/Cft. | 3025 | 263175 |
Crush | 150/Cft. | 1721 | 258150 |
Roof Insulation, Termite & Water Proofing | |||
Roof Insulation | 249/Sft. | 146 | 36354 |
Termite Proofing | 1700/Liter | 5 | 8500 |
Water Proofing | 114/Sft. | 146 | 16644 |
Excavation & Steel Reinforcement | |||
Excavation & Backfill + Ghassu | 23/Cft. | 3696 | 85008 |
Steel Reinforcement | 258000/Tonne | 3 | 774000 |
Plumbing Works Cold and Hot Water Supply | |||
25 mm o/d Pipe | 107/Rft. | 203 | 21,721 |
32 mm o/d Pipe | 175/Rft. | 81 | 14,175 |
40 mm o/d Pipe | 268/Rft. | 20 | 5,360 |
50 mm o/d Pipe | 402/Rft. | 25 | 10,050 |
Insulation Armaflex | |||
32 mm o/d | 452/Rft. | 41 | 18,532 |
50 mm o/d | 615/Rft. | 25 | 15,375 |
Drainage System Piping | |||
2" Dia. Pipe | 260/Rft. | 81 | 21,060 |
3" Dia. Pipe | 350/Rft. | 81 | 28,350 |
4" Dia. Pipe | 170/Rft. | 122 | 20,740 |
Gas Piping | |||
GI Welded Pipeline 3/4” i/d | 416/Rft. | 152 | 63,232 |
Gas Cock 3/4" i/d | 1335/Unit | 2 | 2,670 |
Pumps and Drains | |||
Booster Pump 0.75 HP | 155000/Unit | 1 | 155,000 |
Submersible Water Transfer Pump 1 HP | 145500/Unit | 1 | 145,500 |
Floor Drains | 1710/Unit | 7 | 11,970 |
AC Drainage System | |||
1" dia Class "E" | 110/Rft. | 137 | 15,070 |
UPVC Pipeline for Sewerage System | |||
6" dia Class "B" | 714/Rft. | 51 | 36,414 |
Electrical Works Switches and Back Boxes | |||
Power Sockets | 1475/Socket | 12 | 17,700 |
Fan Dimmer | 1250/Dimmer | 8 | 10,000 |
Universal Switch Socket | 625/Socket | 24 | 15,000 |
Telephone Sockets (RJ-11) | 595/Socket | 2 | 1,190 |
Distribution Board | 110741/Unit | 1 | 110,741 |
TV Sockets | 495/Socket | 5 | 2,475 |
Switch Boards | 1390/Board | 24 | 33,360 |
Conduits & Accessories | |||
3/4” dia. Electrical PVC Conduit with accessories | 30/Rft. | 1013 | 30,390 |
1” dia. Electrical PVC Conduit with accessories | 31/Rft. | 304 | 9,424 |
1.5” dia. Electrical PVC Conduit with accessories | 41/Rft. | 35 | 1,435 |
2” dia. Electrical PVC Conduit with accessories | 50/Rft. | 41 | 2,050 |
PVC Ceiling Fan Hook | 550/Unit | 12 | 6,600 |
Wires & Cables | |||
1.5mm Sq. (3/.029) PVC insulated Cu.conductor wire (Light point wiring) | 4944/Coil | 10 | 49,440 |
2.5mm Sq. (7/.029)PVC insulated Cu. conductor wire "Circuit wiring (Normal & UPS) & sockets Split AC | 7931/Coil | 10 | 79,310 |
4mm Sq. PVC insulated Cu. Conductor wire (Power Sockets wiring) Split AC | 12360/Coil | 5 | 61,800 |
Four core 16 mm Sq. PVC insulated Cu. conductor cable (From DB-GF to wapda Energy Meter) | 1494/Rft. | 70 | 104,580 |
Cat 5 for Telephone Cable | 376/Rft. | 51 | 19,176 |
TV Coaxial Cable for TV cable | 357/Rft. | 152 | 54,264 |
Lights, Fans and Chandeliers | |||
Boundary Wall lights | 1692/Light | 2 | 3,384 |
Porch Lights | 1692/Light | 4 | 6,768 |
Bedroom Lights | 1330/Light | 12 | 15,960 |
Bathroom Lights | 1330/Light | 8 | 10,640 |
Open Area Lights | 1330/Light | 10 | 13,300 |
Kitchen Lights | 3500/Light | 8 | 28,000 |
Stair Case Lights | 1400/Light | 6 | 8,400 |
Drawing Room Lights | 3928/Light | 4 | 15,712 |
Living Area Lights | 3928/Light | 8 | 31,424 |
Ceiling Fans | 9500/Fan | 8 | 76,000 |
Exhaust Fans | 5000/Fan | 6 | 30,000 |
Wood, Metal and Tile Works Paint and Ceiling Works | |||
False Ceiling | 130/Sft. | 608 | 79,040 |
Paint | 57/Sft. | 8606 | 490,542 |
Tile Work | |||
Floor Tiles | 310/Sft. | 2140 | 663,400 |
Floor Skirting | 271/Sft. | 748 | 202,708 |
Ceramic Tiles on Walls & Dado | 289/Sft. | 760 | 219,640 |
Wooden Doors | |||
Main Entrance Door | 101701/Door | 1 | 101,701 |
Room Doors | 38420/Door | 4 | 153,680 |
Washroom and Other Doors | 27120/Door | 6 | 162,720 |
Roof and Terrace Doors | 27120/Door | 3 | 81,360 |
Windows | |||
Aluminium Room Windows | 20340/Window | 6 | 122,040 |
Aluminium Bathroom Windows | 13560/Window | 4 | 54,240 |
Metal Works | |||
Staircase and Terrace Railing | 1605/Rft. | 60 | 96,300 |
Main Gate | 132500/Unit | 1 | 132,500 |
Wardrobes & Cabinets | |||
Wardrobes | 78000/Unit | 3 | 234,000 |
Kitchen Cabinets | 108000/Unit | 2 | 216,000 |
Fittings & Fixtures Kitchen | |||
Kitchen Sink | 13500/Sink | 2 | 27,000 |
Sink Mixer | 11300/Mixer | 2 | 22,600 |
Gully Trap Chamber | 3249/Unit | 2 | 6,498 |
Bathroom | |||
Water Closet | 21696/Unit | 4 | 86,784 |
Vanity Basin | 13575/Basin | 4 | 54,300 |
Basin Mixer | 12200/Mixer | 4 | 48,800 |
Muslim Shower | 2830/Unit | 4 | 11,320 |
Shower Set | 36160/Unit | 4 | 144,640 |
Toilet Paper Holder | 1356/Unit | 4 | 5,424 |
Beveled Edge Mirror | 7040/Mirror | 4 | 28,160 |
Soap Dish | 1083/Dish | 6 | 6,498 |
Geyser & Manhole | |||
Geyser | 32500/Unit | 1 | 32,500 |
Manhole | 5445/Unit | 2 | 10,890 |
Listed below are among the cons of the chokhat:
10 Marla House Construction cost in Pakistan
The cost of constructing a 10-marla house in Pakistan is higher than that of a 5-marla house. The estimated cost for building a ten-Marla house in Pakistan is around PKR 45-60 lakh. The price includes the construction material, labour, and other miscellaneous expenses.
The ten Marla house design options include single-story and double-story houses. The construction of a 10-Marla house in Pakistan requires a detailed house map and plan approved by the relevant authorities.
For 10 Marla houses, the expenditure on the building is almost the same as 5 Marla, but its plan and layouts decide how the expenses are cut. However, in general, the cost is double for ten Marla houses.
If you want to build a double-storey house on a ten-Marla plot, the estimated cost is around PKR 55-70 lakh. The ten-Marla house design includes a detailed plan for the first and second floors and the staircase design.
Frequently Asked Questions
Steel bars made of mild or deformed steel are commonly used in constructing 5-marla houses in Pakistan, depending on the design and specifications.
Lahore’s premium material grey structure rate is PKR 2.18 thousand per square foot.
When constructing an 8-marla property in Pakistan, one can save costs by using locally sourced materials, opting for a simple design with minimal waste and labour expenses, negotiating prices with contractors and suppliers, and avoiding costly finishes and fittings.
Conclusion
The house construction cost in Pakistan is a hefty sum for anyone to invest, but it can be made easier with proper planning, research, and budgeting. It is essential to consider various factors such as location, design, construction material, and labour costs to ensure the project is completed within the budget and on time.
Reviewed by:
Experience hones, but constantly embracing learning and versatility is what brings you to the top. I have had several years of experience behind me regarding sales and team management in a handful of prestigious companies in the country, and even so, I yearn for further professional and personal growth; hence, the various trainings and courses I attended. Read More